OUR PLAN
OUR PLAN
In 2022, we received authorization to expand our storage areas for mining residues and overburden in order to double the site’s production capacity and thereby extend the life of the mine.
Mindful of the ecological impacts, particularly on aquatic environments, we have made a series of concrete commitments to avoid them wherever possible, and to mitigate and compensate for them when avoidance is not feasible.
In accordance with provincial and federal laws and regulations, we have implemented an ambitious and forward-looking compensation plan for local communities, aimed at mitigating potential impacts on:
- Fish habitats
- Wetlands
- Watercourses
An improved concept
Located in an area rich in water bodies, the project had to contend with various constraints. Through a rigorous review of the initial concept, we were able to reduce the area of impacted zones by 53 % compared to the initial scenario, demonstrating our commitment to prioritizing impact mitigation.
OUR PROJECTS
Raising the water level of the Lac des Petits Escoumins
Carried out at la pourvoirie du Domaine du lac Bernier, managed by the Essipit Innu First Nation, this project raised the water level of le Lac des Petits Escoumins by 60 cm to restore it to its historical average level. The work included the reconstruction and raising of dams, as well as the development of spawning grounds, shelters, and thresholds for brook trout. This elevation helped sustainably restore the lake’s ecological functions and reestablish approximately 22.5 hectares of aquatic habitat.
Re-meandering of the Rivière des Escoumins
This project aims to restore the natural processes in the Rivière des Escoumins, which were previously altered by river straightening associated with log driving activities. By restoring these dynamic natural processes, it will create meanders that will sustainably improve Atlantic salmon habitats along more than 90% of the river’s frequented stretch. The work, carried out on three sections of the river (T14, T20, and T28), includes the installation of large woody debris, channel excavation, and the creation of sediment recharge banks. Developed by OBV Haute-Côte-Nord with support from LERGA at UQAC, the project is based on an internationally recognized restoration approach unique to Quebec.
Restoring access to the spawning grounds of Baie Saint-François, Pierreville
This project aims to restore critical habitat for the reproduction of yellow perch and other species in Lac Saint-Pierre by improving hydraulic connectivity with adjacent rivers, water quality, and access to the spawning grounds. These interventions will support the health of fish populations in Lac Saint-Pierre, an important cultural element for the Abenaki community of Odanak, as well as the vitality of local recreational fishing. The work includes restoring fish channels and creating two breaches to the Rivière Saint-François to ensure continuous water flow. Vegetated banks will be established to promote reproduction, and two culverts will be installed to maintain access to the bay for local users.
Applied research fund for atlantic salmon on the Côte-Nord region
QIO will finance the creation of a research fund to study the long-term effects on Atlantic salmon resulting from the development of future fish passages on the Nabisipi River (2027) and Aguanish River (2029), two of our projects included in the current compensation plan.
Led by UQAC, this research program will examine factors such as habitat connectivity and quality, salmon productivity, species interactions, and the integration of Indigenous traditional knowledge. The results will help advance scientific understanding and support the 2016–2026 Atlantic Salmon Management Plan.
Lake trout spawning habitat development at Lake Daviault
Habitat development in the outflow of Lac Daviault and Lac des Huards
This project aims to enhance fish habitat along the waterways connecting Lac Daviault to Lac des Huards and Lac Carheil. The work includes expanding and creating spawning grounds in these outflows to promote brook trout reproduction and support the overall health of fish populations throughout this ecosystem.
Replacement of impassable culverts in the Schefferville area
This project aims to replace, by 2028, two damaged and impassable culverts located at the ends of Lac Maryjo. The work will restore free fish passage and ensure access to habitats upstream and downstream, thereby supporting the health and connectivity of local aquatic ecosystems.
Improving Atlantic salmon migration in the Nabisipi River
The project, proposed by the Conseil de la Nation Innue de Nutashkuan, aims to make Grande Chute (PK 39.2) on the Nabisipi River, located 35 km west of Natashquan, passable. By constructing a fish passage composed of thresholds and pools along the right bank, nearly 75 km of river stretch and 550 ha of high-quality habitat will become accessible, representing over 70% of the river’s salmon production potential.
Improving Atlantic salmon migration in the Aguanish River
The project, proposed by the Conseil de la Nation Innue de Nutashkuan, aims to make Quatrième Chute (PK 16) on the Aguanish River, located 12 km north of Aguanish, passable. The construction of a fish passage composed of thresholds and pools along the left bank will allow salmon to access upstream habitats, representing 93% of the river’s production potential.
Restoring the water level of Lac Mitaine
Proposed by the Nation innue d’Uashat mak Mani-Utenam (ITUM), this project was launched following the July 2017 failure of a culvert at the outflow of Lac Mitaine. It aims to restore the lake’s water level—an important area for the community—and improve aquatic habitat quality. The work includes installing a series of concrete thresholds to raise and stabilize the lake level while allowing fish passage.
Development of riparian buffers in the outflow of Lac Perchard (Fermont)
This project, carried out in the summer of 2025, involved planting vegetation along portions of the banks of the Lac Perchard outflow, an important fish spawning habitat that runs through the town of Fermont. The goal is to stabilize the banks, reduce sediment and other contaminant inputs, and improve aquatic habitat quality. Over 2,300 native trees and shrubs were planted along the banks to achieve these objectives.
Development of wetland and aquatic habitats at the former Lac Jeannine mine site
To come
Implementation Schedule
Each project follows a rigorous and diligent process, including:
For more information on the implementation schedule
ViewDeveloping with and for host communities
We believe that consultation is a key element in a project’s success. Even if a project is technically sound, it gains value when designed in collaboration with local stakeholders. Communities know their territory better than anyone: their experience and observations help us understand how they use the land and its unique characteristics. Result: projects that are better adapted and more seamlessly integrated into their environment and host community.
FAQ
Why is a compensation plan required for mining operations?
-
It is a legal requirement:
-
Quebec: The Environment Quality Act (LQE) includes measures to protect wetlands and aquatic environments.
-
Federal: The Fisheries Act and the Metal and Diamond Mine Effluent Regulations, administered by Fisheries and Oceans Canada (DFO/MPO), require compensation plans when a project directly or indirectly impacts fish habitat.
These regulations ensure that any environmental loss is offset by concrete and measurable projects.
-
Why are some compensation projects located outside the Fermont area?
-
The process for identifying compensation projects aims to prioritize opportunities within the watershed where the impact occurs and, in the case of fish habitat, to focus on the species affected by the project. In our case, since the region around Fermont already hosts numerous mines and mining projects, many compensation projects have already been carried out in the area. As a result, there are few remaining potential projects that would have a significant impact on the targeted habitats.
With this in mind, we expanded our search radius to identify projects addressing known and priority issues, where the benefits would be substantial, explaining why some initiatives are located elsewhere in Quebec.
Who verifies that the compensation projects are effective?
- Each project undergoes rigorous monitoring for a minimum of five years (years 1, 3, and 5 after completion). If the monitoring reports indicate that objectives are not being met, we commit to implementing the necessary corrective actions and conducting additional follow-ups if relevant. In our effort to achieve a real long-term impact, we also works closely with host communities to ensure that appropriate measures are in place to maintain the sustainability of the projects over time.
In what ways are communities involved in the projects?
- We consult stakeholders and Indigenous communities throughout the planning, implementation, and monitoring phases of our projects. These communities know their territory better than anyone, and their input helps us develop projects that are better adapted and more seamlessly integrated.